An ADB review identified shortcomings on some road construction works and poor quality in engineer's cost estimates. These were caused mainly by inadequate designs or poor contractual works and materials. ADB needs to ensure strict compliance with contractors' contractual specifications. Contractors should be held accountable for poor contract performance or substandard materials before the defect liability period following the contract agreements.