Fiji Ports Development Project (Loan 1902-FIJ)

More rigorous risk assessment during project processing would have allowed for better monitoring of key assumptions during implementation. Related to the above lesson on better consultation, the project should have done a better risk assessment. A key impact assumption overlooked was elimination of the port service charge by shipping agents and companies. Another assumption that shipping agents would not construct their own container yards near Lautoka Port should have been highlighted as a key output assumption for sustainable utilization of the reclamation area financed by the project.

Project Name

Fiji Ports Development Project (Loan 1902-FIJ)

Project Number
32525-013
Report Date
Report Source
Independent project evaluation