It is important to effectively manage the timing of investment in transmission capacity particularly on energy generation investments that are undertaken to meet electricity demands. This will involve a careful sequencing of activities and investments. This requires having a longer-term perspective on the energy needs or gaps in the project area to facilitate better timing and project sequencing.
Project Name
Rajasthan Renewable Energy Transmission Investment Program (Tranche 1)
Project Number
45224-003