Delays in land acquisition could bar projects from proceeding with civil works as planned. Because of this experience with contract package (CP) 2, it was decided that at least 50% of the land requirement for C5 will be acquired before contract award. The strategy proved effective in minimizing Implementation delays and should be considered in future projects.