Southern Road Connectivity Project

Delays in land acquisition could bar projects from proceeding with civil works as planned. Because of this experience with contract package (CP) 2, it was decided that at least 50% of the land requirement for C5 will be acquired before contract award. The strategy proved effective in minimizing Implementation delays and should be considered in future projects.

Project Name

Southern Road Connectivity Project

Project Number
47182-001
Report Date
Report Source
Self-evaluation
Country
Report Rating
Applicability
Project Cycle Stage
Implementation
Topics