Road Rehabilitation-2 Project

The procurement process for consultancy services and civil works was too long in spite of approval by ADB to advance corresponding action. ADB and the executing agency should have agreed on the length of the procurement process, which was already set in the ADB procurement guidelines. The delay in core team consultant procurement led to national consultants being tapped to proceed with the project and avoid delays. While not apparent, this could have led to shortcuts in road design being taken, such as the absence of geotechnical studies in road sections with difficult terrain and soil conditions.

Project Name

Road Rehabilitation-2 Project

Project Number
34159-013
Report Date
Report Source
Validation of self-evaluation
Country
Report Rating