Adequate stakeholder coordination during project design could have prevented an overlap between the drainage rehabilitation and maintenance component of the grant and the Nuku’alofa CBD Reconstruction Project.
Project Name
Integrated Urban Development Sector Project
Project Number
38160-032
Report Date
Report Source
Validation of self-evaluation
Country
Sector