Lae Port Development Project

ADB resident mission should be more proactive in monitoring project implementation. It is contingent on the resident mission to assist the executing agency in identifying corrective measures and even use its technical resources to assist in resolving issues. The delay due to unresolved resettlement issues took too long to solve resulting in increased project cost. With local knowledge and experience, the resident mission would be in a good position to identify options in resolving such issues.