Appropriate formulation of DMF facilitates accurate measurement of project performance and achievements. A clear alignment of data and logical framework on performance targets and indicators conforming to each subproject provides a correct measurement on project’s intended results and overall impact. All impact indicators were focused on Anning, but available data were for either Gansu province or Lanzhou, making it difficult to measure these indicators as required.