Skip to main content
Evaluation Lessons
  • Home
  • Countries
    • Afghanistan
    • Armenia
    • Azerbaijan
    • Bangladesh
    • Bhutan
    • Brunei Darussalam
    • Cambodia
    • China, People's Republic of
    • Cook Islands
    • Federated States of Micronesia
    • Fiji
    • Georgia
    • Hong Kong, China
    • India
    • Indonesia
    • Kazakhstan
    • Kiribati
    • Kyrgyz Republic
    • Lao People’s Democratic Republic
    • Malaysia
    • Maldives
    • Marshall Islands
    • Mongolia
    • Myanmar
    • Nauru
    • Nepal
    • Niue
    • Pakistan
    • Palau
    • Papua New Guinea
    • Philippines
    • Republic of Korea
    • Samoa
    • Singapore
    • Solomon Islands
    • Sri Lanka
    • Taipei,China
    • Tajikistan
    • Thailand
    • Timor-Leste
    • Tonga
    • Turkmenistan
    • Tuvalu
    • Uzbekistan
    • Vanuatu
    • Viet Nam
    • Australia
    • Japan
    • New Zealand
  • Sectors
    • Agriculture, natural resources, and rural development
    • Education
    • Energy
    • Finance
    • Health
    • Industry and trade
    • Information and communication technology
    • Multisector
    • Public sector management
    • Transport
    • Water and other urban infrastructure and services
  • Themes
    • Inclusive Economic Growth
    • Environmentally Sustainable Growth
    • Regional Integration
    • Private Sector Development
    • Governance and Capacity Development
    • Gender Equity and Mainstreaming
    • Knowledge Solutions
    • Partnerships
  • About
  • Home
  • Countries
  • Sectors
  • Themes
  • About

Power Transmission Investment Program - Tranche 1

Contract packaging should carefully consider the market conditions while ensuring competition and efficiency.

Project Name

Power Transmission Investment Program - Tranche 1

Project Number
42039-034
Report Date
28 Sep 2021
Report Source
Self-evaluation
Country
Viet Nam
Sector
Energy
Electricity transmission and distribution
Energy sector development and institutional reform
Applicability
Project-level
Project Cycle Stage
Implementation
Topics
Procurement, Contract packaging

Related Lessons

Thorough institutional capacity assessment is a necessary precondition to determining the most appropriate implementation arrangement.


The multitranche financing facility (MFF) is not suitable when the executing and implementing agencies (EAs/IAs) do not have adequate staff…


The main lesson here seems to be that the facilitation of donor coordination by government can play a critical role in ensuring policy and program…


Financial intermediary. The financial intermediary loan modality was an effective mechanism to support implementation of energy efficiency…


Clarify roles and respect existing mandates. Initial delays in implementation of the project were caused by confusion about the roles of new and…


Subscribe to our mailing list

6 ADB Avenue,
Mandaluyong City
1550, Metro Manila,
Philippines

 

Phone: +632 632 4444
Fax: +632 636 2444

Other ADB Websites

ADB Compliance Review Panel
Asia Pathways (ADBI Blog)
Asia Regional Integration Center
Asian Bonds Online
Asian Development Blog
Open Access Repository
Statistical Database System

IED Social Media

LinkedIn

Twitter

YouTube

©2024 Independent Evaluation - Asian Development Bank

Footer

  • About